North Middle School

The North Middle School modernization will remodel the main gymnasium areas, a new 2-story classroom building to accommodate 30 general education classrooms, and a new 1-story administration building, while retaining the recently constructed auxiliary gymnasium. Site work is expected to include new perimeter fencing and upgrades to the track and field.
 
  Location   2514 Rainier Ave., Everett, WA 98201
  Architect   NAC Architects
  Contractor   TBD
  Estimated project cost   $50,100,00
  Estimated completion
  August, 2019
 
Project update as of March 7, 2017
Comments have been returned on the first draft of the Educational Specifications. The site plan and building shape have been finalized and schematic design is well underway. At the April 11 board meeting, staff will present the Educational Specifications and Schematic Design.