,

2010 Capital Levy Projects


 

Athletics building roof and gutter replacement

New asphalt shingle roofing, sheet metal flashing, gutters and downspouts was installed on the athletics building, football press box and the south ticket booth at Memorial Stadium. A fall-restraint system and equipment were included to allow for safer working conditions during roof maintenance.  

  Cost       $309,126
  Project completed 2016
 
 
 

Cascade High School gymnasium floor refinishing

Refinished and partially replaced the gymnasium floor at Cascade High School. It included adding framing supports to the floor in areas where replacement materials were installed. The entire floor was sanded and refinished, and new court lines were installed. This project was funded by 2010 levy funds transferred to the general fund.

  Cost       $73,668
  Project completed 2014
 
 
 

District-wide HVAC controls – Phase 1

The front end heating, ventilation and air conditioning (HVAC) controls were replaced or upgraded at 11 schools and the maintenance building. 

  Cost       $492,402
  Project completed 2016
 
 
 

Everett High School auditorium air conditioning systems upgrades

Replaced the air conditioning unit that served the auditorium with a new high efficiency air conditioning unit.  
 
  Cost       $433,382
  Project completed 2016
 
 
 

Hawthorne HVAC upgrades

Replaced the aging gas fire classroom furnace with high energy efficiency units. Replaced obsolete HVAC controls. Added conditioned air to administration, library and computer lab. 

 
  Estimated cost       $950,000
  Actual cost  $972,431    
  Project completed  2012
 
 

Heatherwood Middle School HVAC and roof replacement

This project replaced aging, inefficient HVAC equipment and installed a building energy management system that provides better control of the indoor environment and reduced energy use. The project also included replacement of the school's roofing system, which had reached the end of its useful life, with increased insulation to improve energy performance. $2,663,966 of the costs for this project were covered by 2010 levy funds, and $32,653 were covered by SCAP funds.
 
   Estimated cost  $730,000
   Actual cost  $2,696,619
   Project completed  2012

 
 

Heatherwood Middle School back-up generator 

Replaced a non-functioning internal standby generator at Heatherwood Middle School with a new generator located outside the building. The generator serves as emergency standby electrical power to the school in the event of a power outage. 
 
  Cost       $163,285
  Project completed 2016
 
 
 

Jackson High School boiler room hydronic piping upgrades

Replaced the existing fittings in the boiler room with welded steel pipe and fittings. This project was funded by 2010 levy funds transferred to the general fund.
 
  Cost       $354,726
  Project completed 2015
 
 
 

Jackson High School chiller upgrade 

Two air conditioning chillers that provided cooling capacity to the HVAC system at Jackson High School were severely damaged during a major wind storm in August 2015. These units underwent major repairs since that time and are now in full operation. Work included replacement of the main control panels, temperature sensors, transducers, current sensors an electronic expansion valves, controllers for the electronic expansion valves; installation of three phase voltage monitoring kits, relay expansion boards, sensor analog boards, and new compressors. This project was funded by 2010 levy funds transferred to the general fund.

  Cost       $183,665
  Project completed 2016
 
 
 

Jackson High School weatherization project

Removed portions of the exterior siding materials that were failing and allowing water penetration and replaced them with a new metal siding system. This project was funded by 2010 levy funds transferred to the general fund.
 
  Cost       $450,308
  Project completed 2014
 
 
 

Lowell and Madison Elementary Schools  - Flooring Replacement

Replaced the flooring in the cafeteria, on the stage and in seven classrooms at Lowell Elementary School and the annex building at Madison Elementary School.
 
  Cost   $260,622
  Project completed 2013
 
 
CLOSE