Other Projects

Synthetic Turf Fields at JHS and CHS

This project includes installation of new synthetic turf at the existing football fields at Cascade HS and Jackson HS, including new drainage and irrigation/wash-down systems.
 
  Location   HM Jackson HS – 1508 136th Street SE, Mill Creek, WA 98012
Cascade HS – 801 E. Casino Road, Everett, WA 98203
  Architect   D.A. Hogan & Associates
  Contractor   TBD
  Estimated project cost   $4,250,000
  Estimated completion
  September 2017
  Funding source   non-bond, non-levy
 
Project update as of March 8, 2017
Schematic design is complete for both sites. The design team is working with the City of Everett to determine the design and engineering requirements for code related drainage issues related to the Cascade HS field.
 
 

Stadium Reader Board and CRC Exterior Signage

Installation of a new reader board at Everett memorial stadium to replace the outdated reader board in front of the stadium at 3830 Broadway Ave, Everett, WA, which is deteriorated and non-functional. Also included are two new exterior illuminated building signs at the district’s Community Resource Center, 3900 Broadway Ave, Everett WA.
 
  Location   3830 & 3900 Broadway Ave, Everett, WA 98201
  Architect   Dykeman
  Contractor   Stadium Reader Board - Daktronics
CRC Exterior Signage - TBD
  Estimated project cost   $250,000
  Estimated completion
  September 2017
  Funding source   Rent, Miscellaneous
 
Project update as of March 8, 2017 
A concept for the reader board and building signs has been developed. Use permits for the proposed signage have been submitted to the city for approval.
 

Longfellow Site Redevelopment 

This project includes demolition of the Longfellow and Annex buildings located at the north end of Everett Memorial Stadium, and redevelopment of the site into new parking areas for school and community use. The Longfellow building was built in 1911 and the annex was constructed in 1956, and expert analysis has shown they would be too expensive to upgrade and maintain in the long term. Leading up to this point, the district has already completed an extensive real estate marketing effort in an unsuccessful attempt to locate a prospective purchaser of these buildings with the financial backing to complete a purchase and sale, or lease, of the property. Before proceeding with demolition, the district is required to perform an environmental review and to document the historical character of these buildings.
 
  Location   3715 Oakes Ave, Everett, WA 98201
  Architect   Botesch, Nash and Hall Architects
  Contractor   TBD
  Estimated project cost   $750,000
  Estimated completion
  Summer 2017
  Funding source   Rent, miscellaneous
 
Project update as of March 8, 2017
The design team submitted to the city on March 6 for the permits. The land use consultant submitted the environmental documents and the historic property report to the City of Everett and the State on March 6. On April 11, the board will be asked to approve the call for bids for this project.
 
SEPA Notification:
 

174th Street SE Site Purchase

Purchase property adjacent to the 180th St. SE Site to accommodate a roadway to the north (access to 174th St SE) and athletic fields for a future high school.
 
  Location   4328 & 4400 174th St. SE, Bothell, WA 98012
Varies
  Real Estate Consultant   TBD
  Consultants – Land Use   Brent Planning Solutions
  Estimated project cost  
$3,750,000
$1,220,000 – Accepted offer
  Estimated completion
  May, 2017
  Funding source   Rent, miscellaneous
 
Project update as of March 8, 2017
The board approved the request to declare the structures located on this site as surplus at the January 10 board meeting. The residential structures and out buildings will be demolished to make way for a new drive for Elementary #18. The district continues to negotiate the purchase of additional properties along 174th St SE. The district has obtained updated appraisals on the remaining four properties. The district has made a counter offer on one of the properties.
 
 